Dashboard
PM Program ID
PM-BOL_B-CIV-BCN-CE30FE
IFS PM Program key
Description
Revision
Rev 0
IFS revision
Item Class
BOL_B
Bollards Family B
Process Class
CIV
Civil Maintenance
Object IDs
  • • BERTH02.999
  • • BOL03.33
  • • BOL04.33
  • • BOL05.33
  • • +6 more
Sites
BCN
APM Terminals Barcelona
DRAFT

Requires APPROVED status

WTT Steps

Flat Work Task Steps for the PM Program

4 visible / 4 total work steps
Generated WL/WTT assignments are stale. Save + Generate to recalculate colors and mappings.
RankGlobalGOS ComponentStageTypeDurationDowntimeQtyTriggersWork ListWTTWork InstructionExtended Instruction
Needs regenerateNeeds regenerate
Materials and resourcesWL: not generated; WTT: not generated
Step Materials rolled to generated Work Lists
Staged for next generation
Part NoDescriptionQtyUOM
No materials yet. Add a row to stage parts for this Work Step.
Proposed and selected resources
ProposedSelectedTechsWorkingDown
BCN-MECH
BCN Mechanical resource group
Using proposed - BCN Mechanical resource group
Generated Work Lists: none yet
Needs regenerateNeeds regenerate
Materials and resourcesWL: not generated; WTT: not generated
Step Materials rolled to generated Work Lists
Staged for next generation
Part NoDescriptionQtyUOM
No materials yet. Add a row to stage parts for this Work Step.
Proposed and selected resources
ProposedSelectedTechsWorkingDown
BCN-ELEC
BCN Electrical resource group
Using proposed - BCN Electrical resource group
Generated Work Lists: none yet
Needs regenerateNeeds regenerate
Materials and resourcesWL: not generated; WTT: not generated
Step Materials rolled to generated Work Lists
Staged for next generation
Part NoDescriptionQtyUOM
No materials yet. Add a row to stage parts for this Work Step.
Proposed and selected resources
ProposedSelectedTechsWorkingDown
BCN-ELEC
BCN Electrical resource group
Using proposed - BCN Electrical resource group
Generated Work Lists: none yet
Needs regenerateNeeds regenerate
Materials and resourcesWL: not generated; WTT: not generated
Step Materials rolled to generated Work Lists
Staged for next generation
Part NoDescriptionQtyUOM
No materials yet. Add a row to stage parts for this Work Step.
Proposed and selected resources
ProposedSelectedTechsWorkingDown
BCN-ELEC
BCN Electrical resource group
Using proposed - BCN Electrical resource group
Generated Work Lists: none yet
Maintenance Trigger Definitions
NameKindTrigger definition
ParameterValue
ParameterValue
ParameterValue